LIST OF WORK (PER LOCAL CODE) FOR LOCAL SUBCONTRACTORS TO THE PROJECT AREA.
EXCAVATING:
1. EXCAVATING SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF LOCAL BUILDING DEPARTMENT AND AS REQUIRED.
CONCRETE, FOOTINGS AND FOUNDATIONS:
1. ALL FOOTINGS SHALL BEAR ON UNDISTURBED SOIL OR APPROVED COMPACTED FILL WITH A SOIL BEARING CAPACITY OF 3000PSI.  ALL FOOTINGS SHALL EXTEND A MINIMUM DEPTH OF 3’6” BELOW FINISHED GRADE OR AS INDICATED ON THE BLUE PRINTS; 8’’ THICK 9’ HIGH.
2. THE SUBCONTRACTOR SHALL BE RESPONSIBLE TO COORDINATE PLACING OF ALL SLEEVES IN CONCRETE WALLS FOR THE TELEPHONE, PLUMBING, ELECTRICAL AND MECHANICAL TRADES; IF NEEDED.
    CRAWL SPACE SLAB:
1. INSTALL FOIL WITHIN THE EXCAVATED SOIL.
2. DISTRIBUTE GRAVEL APPROXIMATELY 4” THICK.
3. POUR MINIMUM 2” CONCRETE USING A SIX BAG MIX.
4. DRAIN SYSTEM, GARAGE SLAB 22X30, DRIVEWAY 22x31, WALKWAYS,
WATER AND SEWER:
1. PROVIDE ALL LABOR AND MATERIALS FOR WATER AND SEWER SYSTEM, AS REQUIRED BY LOCAL BUILDING DEPARTMENT.
HEATING AND A/C SYSTEMS:
1. INSTALL NEW FORCED WARM AIR FURNACE AND COOLING SYSTEM. FURNACE AND DUCT WORK IN THE BASEMENT ONLY. THE FIRST FLOOR IS DONE! INSTALL FLUE SYSTEM.
2. ALL DUCT-WORK SHALL BE SIZED TO HANDLE THE REQUIRED AMOUNT OF AIRFLOW.
3. ALL CONNECTIONS SHALL BE SEALED WITH METAL FLANGE JOINTS.
4. SUPPORT DUCT WORK @ MAXIMUM 4’-0” O/C PROVIDE FIRE STOPPING FOR ALL PENETRATION BETWEEN FLOORS.
5. THE NEW FURNACE SHALL BE SIZED TO HANDLE THE REQUIREMENTS OF THE STRUCTURE.
6. INSTALL 50-GALLON WATER HEATER WITH FLUE SYSTEM.
PLUMBING:
1. IN THE CRAWL SPACE ONLY (FROM FLOOR BEAMS TO THE SEWER ONLY). THE FIRST FLOOR IS DONE!
2. INSTALL SUMP PUMP.
3. INSTALL ANY REQUIRED GAS LINES.
4. ONE WORKER FOR ONE DAY; CALCULATE THE COST OF ONE WORKER FOR ONE DAY TO FINALIZE CONNECTIONS.
ELECTRICAL:
1. PROVIDE ALL LABOR AND MATERIALS FOR A COMPLETE AND FUNCTIONAL ELECTRICAL SYSTEM TO THE HOUSE; CONNECTING ELECTRICAL SERVICE AND METER BOX.
2. CONNECT ELECTRICAL FUSE BOXES TO THE POLE ONLY.
3. ONE WORKER FOR ONE DAY; CALCULATE THE COST OF ONE WORKER FOR ONE DAY TO FINALIZE CONNECTIONS.
CRANE AND OPERATOR:
1. PROVIDE WAGES FOR THE CRANE AND OPERATOR PER HOURLY, DAILY OR PER PROJECT (MY PREFERRED OPTION).
CARPENTRY WORK:    
1. CONSTRUCT GARAGE AND PORCH; SIDING, SOFFIT, FASCIA AND SHINGLES SUPPLIED BY US.
Applications: form download.  

BLUE PRINTS/FLOOR PLANS.
PLAT OF SURVEY.

Translate This Site.

Recent Videos

6196 views - 0 comments
13734 views - 0 comments
14130 views - 6 comments
14620 views - 0 comments